New Year Expansion Update

Many co-op supporters have been asking where we are in the expansion project. We are currently working through the approval process. We are seeking a zone change and have to complete Design Review with the City of Astoria and the Mill Pond Home Owners Association.

The next big step is approval from the City Planning Commission on Wednesday January 24th at 6:30PM at City Hall. I’d love to have as many of you there as possible to make sure that the Planners know that there is broad community support for our project (we know there is!). We have a City Staff recommendation, which typically bodes well for applications to the Commission, but your presence will help tremendously! The public notice for the planning commission meeting can be found here: http://astoria.or.us/assets/dept_3/pm/pdf/1-24-18%20email.pdf

With approval from the Planning Commission our zone change will go to the City Council on February 19th. I’ll share those details subsequently.

Overall timeline for the project is probably pushing us into Spring of 2019 for opening. But the timeline is fluid and trust we are working very hard to move us into the new space as soon as possible. Other ongoing work includes securing bank financing, finalizing our store layout and fixture plan and much more.

Looking forward to seeing a bunch of you at the January 24th meeting at City Hall! Here’s to a healthy and cooperatively prosperous 2018!

Cheers, Matt Stanley/Co-op General Manager